The preparatory works on ground excavation and stabilization are completed.

Upon completion of preparatory works, a large amount of the main construction and installation works was performed on site. 

f1_1These include:

  • Stabilization of soft and unstable bottom soils, volume over 215,000 m2;
  • Excavation in the areas intended for arrangement of track road dressing, volume about 180,000 m3 ;
  • Laying of underground utilities (storm water and sanitary sewerage) – over 6200 running meters of pipelines;
  • Construction of drainage systems (over 3,000 running meters);
  • Bank for the natural grandstands made of loamy soil, volume over 200,000 m3;
  • The sand body of track roadbed, volume over 600,000 m3.

High rate of works performance given their proper quality are ensured by employment of high-efficiency construction machinery (excavators, bulldozers, graders, etc.).