The work speed of construction of traffic interchange on the 57th km of highway M-5 «Ural» significantly increased.

In May major works were performed on roadbed filling at the exits of the interchange and at new construction site of М-5 "Ural", the works on arrangement of sand bedding course and macadam base commenced. In the nearest time it is planned to start works on laying of asphaltic concrete, installation of edge trays and curb stones.

We signed the contracts with subcontracting organizations for arrangement of water discharge structures, installation of road signs, barrier railing, grassing, road markings, arrangement of lighting.

 

Photographic materials on works progress are given in section "Our projects".