Construction of the 2nd start-up facility of highway M-5 Urals on the section from the Small Moscow Ring Road up to Ulianino village.

A state contract was concluded on December 16, 2012 for construction of the 2nd start-up facility of the detour around Ulianino village. The section as currently under construction will connect the traffic interchange on the 57th km of highway M-5 Urals (1st start-up facility) with Starnikovo-Tatarintsevo motor road and an access to highway M-5 Urals around the 69th km of the highway. Construction of 1 bridge, 2 overhead crossings, 5 structures for connection of isolated territories are planned on the section. The quantity of fill comprises approximately 1.6 million cub. meters of soil. The works are planned to be completed in June 2013.

Read more: Construction of the 2nd start-up facility of highway M-5 Urals on the section from the Small...


Реконструкция мостового перехода 25 км ММК.

ООО Русско-германское СП «Автобан» заключило контракт на выполнение работ по устройству подходов к мостовому переходу через р. Москва (25 км ММК) расположенного в г. Бронницы. Сроки производства работ по контракту составляют 11 месяцев и основные виды работ должны быть выполнены до 1 ноября 2012 года.


Traffic interchange on the 57th km of M-5 «Ural» highway.

On October 27 the traffic was allowed on the overpass, the dismantling of the temporary detour road and construction of the terminal section of the interchange was started.

The construction is planned to be completed in accordance with the schedule – in November 2011.

Performance of “Formula-1” facility works

A set of works for laying of the upper layer of the coating made of porous coarse-grained road concrete mix on the main tracks, service tracks and in the paddock area.

The work for installation of barriers, perimeter fences and FIA barriers is being performed. The facility is being prepared for wintertime shutdown.


The work for construction of the traffic interchange on the 57th km of M-5 “Ural” highway is continued.

The laying of the road concrete coating on the overpass is complete. The laying of road concrete coating on the Moscow Small Ring Road sections and interchange exits, installation of the lighting supports and drainage facilities is about complete. Installation of the barriers and reinforcement of roadsides has started. In the end of the month it is planned to turn the traffic back to normal scheme.