Performance of works for the Formula-1 Project

Works for installation of delivery infrastructure networks and laying of cable systems for communication circuits are currently drawing towards completion on the territory of the race track.

Read more: Performance of works for the Formula-1 Project


Works for construction of a traffic interchange on the 57th km of M-5 “Urals” motorway are continued.

Works for construction of the road dressing, roadbed fill-slope protection and installation of drainage facilities are currently being performed at the traffic interchange. The works for land filling of the cones of the overhead crossing are complete, and asphalt concrete pavement will be constructed upon it in the nearest future. Construction of a temporary bypass road will be completed in the first half of August with traffic switched to that road, which allows us to complete the work package on the Moscow Small Ring Road on the side of Bronnitsy


Construction of a traffic interchange on the 57th km of M-5 “Urals” motorway

The final phase of the land filling operations for the earth roadbed was started in June (some 85% of the overall amount was filled). Works for construction of the macadam base and lower layers of the asphalt-concrete pavement are continued. Works for land filling of the cones of the overhead crossing, installation of curb stones, drainage facilities, covering of roadbed fill-slopes with vegetable soil and installation of illumination poles were started.

Read more: Construction of a traffic interchange on the 57th km of M-5 “Urals” motorway


Implementation of the GPS monitoring system for motor transport and road building machinery is continued.

Autobahn has a system of GPS monitoring of motor transport and road building machinery implemented. The system allows to track movement of machinery in real time, and also to perform control over fuel consumption. Introduction of the system allowed to save over 1 million rubles during the first half-year of 2011.

Fuel control sensors and navigation systems were installed on 24 units of machinery starting from the end of June and throughout July.


Performance of works for the Formula-1 Project

Works for installation of delivery infrastructure networks are currently drawing towards completion on the territory of the race track.

 

Read more: Performance of works for the Formula-1 Project